Many builders choose nails because they re easier to.
Install cedar shingle siding nails.
Attach the shake with a pair of 5d galvanized box nails and a shingle hatchet or hammer.
The nails install 6 inches down from the upper thin edge of the shake and each is 1 inch from the outer.
Add the ridge cap across the peak of the roofline.
Step 5 attach the shingles with 1 inch roofing nails.
Installing cedar shakes is pretty much the same as installing shingles.
Whether you install clapboard t1 11 cedar shakes or board and batten siding on your house you can attach it with either nails or screws.
My local hardware store does not sell 3 1 2 ring shanked so will i be ok.
1 2 crowns is the worst choice you can make for instaling cedars on a wall.
Design build repair restore.
Install shingles using 2 weather resistant nails.
As you can see installing cedar shingles isn t a difficult process.
Use 2 nails per shingle at about 3 4 1 9 cm from each edge and 1 2 5 cm above the butt line of the overlapping shingle.
Hello i will be installing 3 4 cedar siding this weekend either t g or bevel.
I will be needing 3 1 2 nails to do so.
If shingles are wider than 8 20 4 cm use 2 additional fasteners driven 1 2 5 cm apart near the center of the shingles.
Nail one of the shingles to the sheathing so it extends to the line then use a level to install the rest of the shingles in that row with their ends flush with each other.
For staples use 7 16 1 1 cm minimum crown.
A few questions i have 1 whats the reccomended nail.
Apply both nails 3 4 inches from the edge of each shake or shingle and about 1 1 2 inches above the exposure line.
They ll rust thru before the shingle fails mike smith rhode island.
Nails should be long enough to penetrate underlying materials in the cedar shingles at least 3 4 inches or all the way through.
Use a chalk line to align the starter course of cedar shingles.
This is when each piece of cedar siding covers half of the one below it much like staggering and layering on cedar siding on top of one another to provide a scale like appearance.
Use two fasteners to apply each certi label shingle or shake.
I know that it needs to penetrate 1 1 2 into the stud.
Add remaining courses until you reach the roofline.
Use hand nails a carefully set up and adjusted siding gun or if it must be staples use wide crown across the gap of two so one leg is in each shingle.
The traditional way to install cedar shakes is through a method called single coursing.
Install the first course directly on top of the starter course.
This will be my first time so i would love a few pointers to get me on the right path.